Why you need a building contract

While Kiwis are known for our ‘she’ll be right’ attitude, when it comes to renovating or building your home that kind of approach could see you in a sticky situation if things go awry. And we don’t want that!

By law, if you’re a homeowner doing residential building work that costs $30,000 or more (including GST), you must have a written contract with your building contractor.

But even if the work you have planned costs less than $30,000, New Zealand Certified Builders recommends you always use a building contract. Why? Because when it comes to your biggest investment, it is always a case of better safe than sorry.

A written contract protects you – it sets out both yours and your builder’s rights and obligations. When done right, it helps ensure the work done meets your expectations and that key matters are agreed before the work begins. And while verbal and handshake agreements are legally enforceable, they leave a lot of room for uncertainty about what has been agreed. That’s why we always recommend you talk your contract through with your builder, then ensure you have it all down in writing, too.

A written contract is good for:

  • confirming the price of the build
  • confirming any subcontractors and clearly defining their roles
  • setting start and finish dates for your work
  • planning your payment schedule
  • defining the quality of work required
  • specifying materials and products for your build
  • confirming who pays council fees
  • understanding the process to follow if there are defects
  • detailing simple procedures for disputes
  • stating any ongoing maintenance work required
istockphoto 2000

There are multiple types of contracts you could have with your builder, which we have
detailed below.

Fixed Price+

A Fixed Price+ contract is used when an aspect [or all] of a project has a quoted element to it. If there are variations to the quote, this contract allows flexibility to accommodate that, while still maintaining payment security. The deposit is held by the builder during construction and balanced at the time of final invoice.

Cost & Mark-up

This type of contract is used when the total price payable for the building work is not fixed, specified, or known at the time of entering into the contract. Instead, progress payments and the final contract price are calculated by reference to the actual costs incurred by the builder, as the work is carried out, with a margin added for the builder’s administration, overhead and profit.

Renovations

A contract for renovations is similar to a standard building contract, except for three main differences, which we’ve detailed below.

Firstly, the builder only gets possession of the part of the building he is working on. Secondly, the owner always takes out the contract work insurance. Thirdly, if you are charging on the basis of completing defined stages of the works, those stages have been left blank so you can fill them out to fit the requirements of the project.

Once you’ve selected the type of contract you’ll use, you need to decide who will manage the project – this can be either the builder (full contract) or yourself (labour-only contract). The differences between these two types of contracts are outlined below.

Full contract

In a full contract, for all projects over $30,000, the builder becomes the ‘main contractor’ and will be project manager for the whole building process. They may take care of:

  • getting a building consent
  • supplying and arranging all building materials and products
  • hiring subcontractors e.g. plumber, electrician, or tiler
  • health and safety on-site
  • working with the architect or designer
  • arranging council inspections at the necessary stages
  • letting council know if variations or amendments arise during the project
  • arranging for the final inspection and issue of the code of compliance certificate
  • anything else you discuss, agree on, and include in the contract

Under a full contract, the builder is responsible for the quality of both their own work and their subcontractors’ work. You are still able to work with the builder to make decisions that may arise during the build.

Labour-only contract

If a full contract is too extensive for your project, you can opt for a labour-only contract.

This type of contract should only be used if you, or a specialist project manager appointed by you (such as an architect, engineer, or another builder) are going to manage the overall project. Project management includes buying materials and hiring contractors, as well as co-ordination of contractors’ activities on-site. A labour-only contract allows for the supply of incidentals (low value) and variation rates. Margins are also agreed upon in the contract. Your contracted tradespeople will only be responsible for the trade you have hired them to complete and you will need contracts with each tradesperson.

Unless you have arranged for your designer to take on a project management role, you may be responsible for:

  • getting building consent
  • making sure the work meets Building Code requirements
  • buying and managing materials, products, and supplies
  • finding and hiring other tradespeople you may need
  • health and safety on-site
  • arranging council inspections
  • communicating any variations or amendments to your council

Make sure each tradesperson’s role is clearly defined in any written contracts you may have with them, as this helps minimise any possible miscommunication further down the track. And, of course, each tradesperson you hire is still obligated to produce quality work.

If you fail to organise the building process properly, such as hiring subcontractors, buying materials, or arranging building inspections, then each tradesperson may be held up in completing their roles within the project. This can have serious financial implications for both you and your tradespeople in the long run.

If you don’t manage projects of this type regularly, it can be overwhelming, which is why we’re here to help. Our NZCB builders are used to dealing with contracts and all the details involved in any level of building project.

To find a New Zealand Certified Builders professional for your next building project use the Find A Builder search function on www.nzcb.nz

Latest News

NZCB Nelson Andy 04

Resilience, regulations and revelations

August 22, 2025

This article featured in the June 2025 edition of the NZCB InHouse magazine. A team...
iStock-1198797451

What is a 10-year building guarantee?

March 19, 2025

If you’re looking to build your next home, or are undertaking a large-scale renovation, it’s...
dec-blog

How to choose the right builder

March 10, 2025

Building or renovating your home is a big deal. It’s one of the biggest financial...
NZCB Apprentice Trust_JRive

How to get a Building Apprenticeship

March 7, 2025

So, you’re keen to become a builder? Whether you’ve just finished school or looking for...
Builder removing old fiberglass wall insulation.Home improvement companies traded asbestos insulation for fiberglass after finding out the harmful effects asbestos has on lungs.

In the News: NZCB welcomes new proposals on H1 building regulations

December 10, 2024

Building Minister Chris Penk has responded to concerns raised by NZCB about a potential rollback...
Certfifed Builders

In the News: Get in early to book your builder

November 2, 2024

Falling interest rates are prompting a surge in new building projects, with more than 9,000...